In the latest version of the BRUKL document There is a a new section "EPBD (Recast): Consideration of alternative energy systems. It gives negative responses to the three questions of consideration, evidence and measures proposed as a default.
1) Should I be asking my client these questions? - one assumes yes.
2) How do I enter the responses in ApacheSim?
Thanks.
BRUKL - EPBD (Recast) ?
-
paulshipley
- VE Newbie

- Posts: 2
- Joined: Tue Feb 19, 2013 11:05 am
Re: BRUKL - EPBD (Recast) ?
Hi Paul,
Yes, our developers haven't yet created the interface
Yes, our developers haven't yet created the interface
Re: BRUKL - EPBD (Recast) ?
Has this interface been created yet?
Re: BRUKL - EPBD (Recast) ?
Not yet. It will hopefully be done for our VE Compliance (UK Regulations update) release in April.