Hotel Baseline PTAC system EER

Post by geshen516 »

dear all here

As for PTAC system, the system COP(EER) includes the supply air fan and condenser fan power.
Is this considered in LEED PRM navigator?

According to observation, the narrative in "DX Coolign (types)", it seems IES has considered this.
However, when I looked through the baseline models for 4 directions, all the COP are same, 2.56 for PTHP>15kBTu/h and 2.88 for PTHP 7-15kBTu/h.
May I know how these two numbers are derived? or has these two number approved by GBCI?
Any advice is welcome

Best Regards
zhang xiangjing
ESD, ARUP Singapore
geshen516
VE Student
VE Student
Posts: 40
Joined: Mon Oct 06, 2008 1:17 pm

Re: http://www.canadagooseparkaoutleta.com/#065904

Post by geshen516 »

lkgclycbp wrote:trtwr jwcaa rnphi Canada Goose Jackets
idxkx fenfx zynnz Canada Goose Online
sndsk pcsvy vapns http://www.canadagooseparkaoutleta.com/

bxqri madju dtvej
Canada Goose Jacket
qqshj mkzju gjten
Canada Goose Parka
dicha czkom xzxmw http://www.canadagoosesparkasale.com/
Could you type in English?
totally can not understand
geshen516
VE Student
VE Student
Posts: 40
Joined: Mon Oct 06, 2008 1:17 pm

Re: Hotel Baseline PTAC system EER

Post by geshen516 »

One more question, how are these capacity numbers related to ASHRAE 90.1
Say, 7kBTu/Hr = 7*0.2928=2.05kW; 15kBTu/Hr=4.4kW. There is no such category in ASHRAE.

Please clarify.

Thanks

geshen516 wrote:dear all here

As for PTAC system, the system COP(EER) includes the supply air fan and condenser fan power.
Is this considered in LEED PRM navigator?

According to observation, the narrative in "DX Coolign (types)", it seems IES has considered this.
However, when I looked through the baseline models for 4 directions, all the COP are same, 2.56 for PTHP>15kBTu/h and 2.88 for PTHP 7-15kBTu/h.
May I know how these two numbers are derived? or has these two number approved by GBCI?
Any advice is welcome

Best Regards
zhang xiangjing
ESD, ARUP Singapore