Hi IES,
I have two floors modelled that I now wish to produce separate EPCs for (the client changed his marketing).
1) How do I 'switch off' zones to focus the analysis only on the remaining floor?
2) How does IES handle the adjacencies? i.e. if I swicth off the upper floor, does IES assume the lower floor now has adiabatic ceiling adjacencies, or do I have to manually indicate this?
Best
Paul