Do Large Extensions Require an EPC by Default?

Posted: Tue Apr 28, 2015 12:04 pm
by RossThompson87
Hi,

I am working on a project where an office is being extended.

The extension is >100m2 and >25% of the existing floor area. It is not designed to be used separately.

Under Part L, this would be a large extension. So the extension part would then be treated under Part L2a as a new build.

Part L2a then states that new buildings require an EPC.

Hence does the extension need a lodged EPC?

This seems to contradict the EPC guidance as no parts are being added.

Ross

Re: Do Large Extensions Require an EPC by Default?

Posted: Tue Apr 28, 2015 1:44 pm
by Complex Potential
Hi Ross

Page 7 of the following CLG document gives a flow chart to help you determine if an EPC is required in various cases and I believe extensions are covered.

https://www.gov.uk/government/publicati ... ellings--2

Hope this helps.

CP