Waiting Area failing Criterion 3

VE-SBEM for compliance and EPC generation.
Post Reply
Wasted Energy
VE Graduate
VE Graduate
Posts: 93
Joined: Thu Sep 10, 2015 5:58 am
Location: UK NW

Waiting Area failing Criterion 3

Post by Wasted Energy »

I have a 'waiting area' failing Criterion 3 when designated as NCM template 'Reception (Waiting)'.

Now I don't think this should happen as the occupants are clearly 'transient' and exempt as per 2.53.d of L2 from the Criterion and therefore the question of the amount of glazing should not arise.

So how should the space be defined in terms of NCM templates to avoid this 'failure' appearing on the BRUKL?
User avatar
Complex Potential
VE Expert
VE Expert
Posts: 467
Joined: Wed Jan 09, 2013 11:57 am
Location: Bristol, UK

Re: Waiting Area failing Criterion 3

Post by Complex Potential »

You could define the space as general circulation but if the space is cooled it will be subject to criterion 3 regardless of how it is defined.